Skip to main content

Public contracts of the Cantal département · 2022

Rénovation thermique collège st Mamet

Démolition gros oeuvre

€393k
maximum contract amount over 20 months — what was paid on it is not published
Signed on 29 August 2022 · ended around April 2024 · 20 months

That is at most ~€236k a year on average: a maximum too.

Company selected

Cantal ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Aurillac (15000) · headcount 10 to 19 employees · SIREN 337662712

Number 34 by amount of the 212 contracts the Cantal département published for 2022.

Other contracts of Cantal Construction in Cantal

Construction salle de classe collège st cernin2026 · maximum over 10 months91€kTravaux de requalification architecturale et thermique de l’ancien…2025 · maximum over 13 months169€kExtension réfectoire collège la ponetie2022 · maximum over 8 months237€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 7

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.