Public contracts of the Nord département · 2022
Travaux aménagement Utpas lille moulins rue bayard
Gros oeuvre
That is at most ~€413k a year on average: a maximum too.
Company selected
Rabot Dutilleul ConstructionConstruction d'autres bâtiments · registered office Wasquehal (59290) · headcount 500 to 999 employees · SIREN 389612383A contract awarded to a consortium of 2 holders; above, the main holder. With it: Cpsbois. The amount is the whole contract’s: the DECP does not publish each holder’s share.
The competition
Median for this procedure in 2022: 3 bids, across 2458 comparable contracts. Simplified procedure · awarded to 2 companies
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 107 by amount of the 623 contracts the Nord département published for 2022.
Other contracts of Rabot Dutilleul Construction in Nord
Travaux pour le programme de gros entretiens de renouvellement…2022 · maximum over 4 years254€kTravaux d’isolation des coursives entre le rez de chaussée…2022 · maximum over 18 months126€kTravaux pour le remplacement de la veture de façade du bâtiment b…2022 · maximum over 3 years124€kContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Mixte
Published amendments : 9
Subcontracting declared : yes
The 2 lots : 473 €k · 458 €k
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.