Public contracts of Digny · 2021 · Construction and buildings

Renforcement du réseau eau potable hameau du charmoy gonthier

€76k
contract ceiling — what was paid on it is not published
Signed on 27 May 2021 · ended around July 2021 · 2 months

Who won it

TP 28Travaux de terrassement courants et travaux préparatoires · registered office Tremblay Les Villages (28170) · headcount 20 to 49 employees · SIREN 333784296

Number 2 by amount of the 3 contracts Digny published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.