Public contracts of Dinan · 2024 · Professional services

Maîtrise d’œuvre travaux de modernisation parking hôtel de ville

€130k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 12 December 2024 · ended around May 2025 · 5 months

Company selected

Études et Coordination du BâtimentIngénierie, études techniques · registered office Saint-Malo (35400) · headcount 10 to 19 employees · SIREN 312610397

A contract awarded to 2 holders; above, the main holder. With it: Pichouron Yann Architecte. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

5 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 17 by amount of the 27 contracts Dinan published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

The 2 lots : 70 €k · 60 €k