Skip to main content

Public contracts of Dinard · 2026 · Construction and buildings

Construction serres

Gros oeuvre

€342k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 22 January 2026 · running until about February 2027 · 13 months
Ongoing22 Feb 2027

That is at most ~€315k a year on average: a maximum too.

Company selected

Entreprise le GalTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Saint-Symphorien (35630) · headcount 20 to 49 employees · SIREN 377875729

The competition

4 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 10 by amount of the 83 contracts Dinard published for 2026.

Other contracts of Entreprise le Gal in Dinard

Travaux de construction des serres et bâtiments techniques2026 · maximum over 13 months342€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Social considerations : Clause sociale, Critère social

Environmental considerations : Clause environnementale, Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.