Public contracts of Dole · 2018 · Construction and buildings

Réhabilitation et réaménagement de l’école élémentaire Wilson-2e phase de travaux

Démolition · Maçonnerie

€133k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 22 October 2018 · ended around October 2020 · 2 yrs

That is at most ~€66k a year on average: a maximum too.

Company selected

Ortelli et CompagnieTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Brevans (39100) · headcount 10 to 19 employees · SIREN 035550318

Number 9 by amount of the 20 contracts Dole published for 2018. It belongs to the policy Schools.

Other contracts of Ortelli et Compagnie in Dole

Extension Restos du Coeur2022 · maximum over 12 months65€kExtention centre schweitzer / restos du coeur2022 · maximum over 1 month58€kConstruction club house au centre équestre2021 · maximum over 1 month128€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.