Skip to main content

Public contracts of Dole · 2018 · Construction and buildings

Réhabilitation et réaménagement de l’école élémentaire Wilson-2e phase de travaux

Désamiantage

€22k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 19 November 2018 · ended around November 2020 · 2 yrs

That is at most ~€11k a year on average: a maximum too.

Company selected

GCM DemolitionTravaux de démolition · registered office Bouxwiller (67330) · headcount 20 to 49 employees · SIREN 502834997

Number 20 by amount of the 20 contracts Dole published for 2018. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.