Public contracts of Domagné · 2025 · Construction and buildings

Atelier technique

Démolition / Terrassement / Réseaux / Maçonnerie

€50k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 17 November 2025 · running until about January 2027 · 14 months
Ongoing17 Jan 2027

That is at most ~€43k a year on average: a maximum too.

Who won it

Marse ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Acigne (35690) · headcount 10 to 19 employees · SIREN 450437892

The competition

8 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 2 by amount of the 17 contracts Domagné published for 2025.

Other contracts of Marse Construction in Domagné

Réhabilitation thermique de l’école et de la cantine de Domagné2024 · maximum over 21 months34€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.