Public contracts of Doussard · 2019 · Construction and buildings

Construction ponton en bois a glières

€43k
contract ceiling — what was paid on it is not published
Signed on 18 April 2019 · ended around May 2019 · 1 month

Who won it

SikooConstruction d'ouvrages maritimes et fluviaux · registered office Sevrier (74320) · headcount 3 to 5 employees · SIREN 483582755

Number 4 by amount of the 4 contracts Doussard published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.