Skip to main content

Public contracts of Drancy · 2022 · Construction and buildings

Gros oeuvre-Structure

€565k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 28 March 2022 · ended around March 2023 · 12 months

Company selected

T.C BTPConstruction de maisons individuelles · registered office Saint-Denis (93200) · headcount 1 or 2 employees · SIREN 817549546

Number 15 by amount of the 174 contracts Drancy published for 2022.

Other contracts of T.C BTP in Drancy

Lot no1 Gros œuvre-Structure2022 · maximum over 12 months565€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.