Public contracts of Durtol · 2021 · Construction and buildings

Électricité

€60k
contract ceiling — what was paid on it is not published
Signed on 20 April 2021 · ended around February 2022 · 10 months

Who won it

DomelecTravaux d'installation électrique dans tous locaux · registered office Mont-Dore (63240) · headcount 3 to 5 employees · SIREN 432186559

Number 4 by amount of the 6 contracts Durtol published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.