Skip to main content

Public contracts of Elne · 2025 · Construction and buildings

Rénovation énergétique du complexe sportif : charpente métallique et serrurerie

€172k
maximum contract amount over 19 months — what was paid on it is not published
Signed on 5 August 2025 · running until about March 2027 · 19 months
Ongoing6 Mar 2027

That is at most ~€109k a year on average: a maximum too.

Company selected

SAS Beck et CieTravaux de couverture par éléments · registered office Le Soler (66270) · headcount 20 to 49 employees · SIREN 389962416

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Leonard et Olive. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

1 bid received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 14 by amount of the 25 contracts Elne published for 2025. It belongs to the policy Culture, sport and youth.

Other contracts of SAS Beck et Cie in Elne

Rénovation énergétique du complexe sportif d’Elne : isolation par…2025 · maximum over 14 months481€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.