Skip to main content
Qipu

Public contracts of Entre-Deux · 2021

LOT1 VRD

The largest contract Entre-Deux awarded in 2021, out of 2.

Original label (DECP) : « LOT1 VRD » · Contract · Construction and Bâtiment · carried out in 97414

2€M
contract ceiling — what was paid on it is not published
Signed on 27 October 2021 · ended around October 2022 · 1.0 yrs
Ended27 Oct 2022

Who won it

Gestion et Conseil de TravauxSIREN 814139077

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceFerme et actualisable
Published amendmentsnone

Other contracts of Gestion et Conseil de Travaux in Entre-Deux

Travaux de VRD202510.1M€Travaux de VRD20234.4M€Modernisation d’une portion de la rue defaud - lot no1 travaux de VRD20201.4M€Modernisation d’une portion de la rue defaud - lot no3 réseau téléphone2020157k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method