Skip to main content

Public contracts of Épinal · 2024 · Professional services

Maîtrise d’OEuvre pour les Réparations et Améliorations de la charpente de la halle des sports suite à sinistre ; lot unique

€81k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 18 October 2024 · ended around October 2026 · 2 yrs

That is at most ~€41k a year on average: a maximum too.

Company selected

Patrice NormandActivité des économistes de la construction · registered office Saint-Bresson (70280) · headcount 3 to 5 employees · SIREN 514843796

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 25 by amount of the 59 contracts Épinal published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.