Skip to main content

Public contracts of Étaples · 2022 · Other

Extension de l’école élémentaire Jean Moulin et de l’École Primaire Rombly

€49k
maximum contract amount over 10 months — what was paid on it is not published
Signed on 9 November 2022 · ended around September 2023 · 10 months

Company selected

O.T.G (Organisation Technique Gestion)Travaux d'installation électrique dans tous locaux · registered office Formerie (60220) · headcount 10 to 19 employees · SIREN 803878867

Number 46 by amount of the 72 contracts Étaples published for 2022. It belongs to the policy Schools.

Other contracts of O.T.G (Organisation Technique Gestion) in Étaples

Extension de l’école élémentaire jean moulin…2022 · maximum over 2 months49€kRénovation de l’hôtel de ville d’Étaples-sur-mer2021 · maximum over 10 months31€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.