Public contracts of Fillière · 2024 · Construction and buildings

Rénovation et extension de l’école d’Aviernoz

€247k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 4 July 2024 · ended around January 2026 · 18 months

That is at most ~€164k a year on average: a maximum too.

Company selected

Titulaire sans SIRET

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 12 contracts Fillière published for 2024. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

The 5 lots : 98 €k · 66 €k · 61 €k · 11 €k · 11 €k

The filing gives no SIRET for the contractor: since we cannot check it is not a person, the name is not published.

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.