Skip to main content

Public contracts of Fontaine · 2022 · Construction and buildings

Travaux de réhabilitation de la halte garderie george sand

€20k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 2 May 2022 · ended around September 2022 · 4 months

Company selected

SobateTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Saint-Martin-D'Heres (38400) · headcount 20 to 49 employees · SIREN 792677494

Number 40 by amount of the 48 contracts Fontaine published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.