Public contracts of Fontenay-Trésigny · 2025 · Construction and buildings

Construction d’une restauration scolaire et de deux salles de classe maternelles : gros œuvre

€2M
maximum contract amount over 20 months — what was paid on it is not published
Signed on 18 June 2025 · running until about February 2027 · 20 months
Ongoing17 Feb 2027

That is at most ~€1.2M a year on average: a maximum too.

Company selected

Cisco BâtimentConstruction de maisons individuelles · registered office Chelles (77500) · headcount 20 to 49 employees · SIREN 451606610

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Gci Construction. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

9 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 16 contracts Fontenay-Trésigny published for 2025. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 10

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.