Public contracts of Fontenilles · 2021 · Construction and buildings

Bâtiment

€803k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 16 December 2021 · ended around May 2022 · 5 months

Company selected

ModulemFabrication de structures métalliques et de parties de structures · registered office La Magdelaine-Sur-Tarn (31340) · headcount 20 to 49 employees · SIREN 789948148

The largest of the 7 contracts Fontenilles published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none