Skip to main content

Public contracts of Frans · 2024 · Construction and buildings

Extension et restructuration de l’école maternelle de Frans

"Démolition · Gros œuvre"

€88k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 11 July 2024 · ended around January 2026 · 18 months

That is at most ~€59k a year on average: a maximum too.

Company selected

Entreprise LefortTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Gleize (69400) · headcount 10 to 19 employees · SIREN 307321745

The competition

5 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 4 by amount of the 24 contracts Frans published for 2024.

Other contracts of Entreprise Lefort in Frans

Démolition et gros œuvre2024 · maximum over 18 months88€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.