Travaux de rénovation énergétique école de puymaure

Électricité courants forts et faibles

€50k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 10 March 2026 · running until about September 2027 · 18 months
Ongoing9 Sept 2027

That is at most ~€33k a year on average: a maximum too.

Company selected

GapelecTravaux d'installation électrique dans tous locaux · registered office Gap (05000) · headcount 10 to 19 employees · SIREN 527613160

The competition

3 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 33 by amount of the 39 contracts Gap published for 2026. It belongs to the policy Schools.

Other contracts of Gapelec in Gap

Travaux de construction d’un abattoir avicole2025 · maximum over 6 months108€kRéhabilitation de du groupe scolaire beauregard a Gap2024 · maximum over 18 months108€kConstruction petite crèche 24 places électricité courant fort / courant…2024 · maximum over 10 months43€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte