Skip to main content

Public contracts of Gap · 2024 · Construction and buildings

Réhabilitation de du groupe scolaire beauregard a Gap

Plomberie-chauffages-ventillation

€44k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 30 July 2024 · ended around January 2026 · 18 months

That is at most ~€30k a year on average: a maximum too.

Company selected

La Gapencaise de ChauffageTravaux d'installation d'équipements thermiques et de climatisation · registered office Gap (05000) · headcount 6 to 9 employees · SIREN 387150238

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 121 by amount of the 128 contracts Gap published for 2024. It belongs to the policy Schools.

Other contracts of La Gapencaise de Chauffage in Gap

Réhabilitation de l’école paul emile victor élémentaire2025 · maximum over 18 months107€kTravaux d’extension du Hall de la Blâche2019 · maximum over 5 months29€kConstruction de vestiaires pour le stade bayard2019 · maximum over 4 months19€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.