Restructuration et extension du conservatoire : terrassement et démolition

€668k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 10 March 2020 · ended around June 2021 · 15 months

That is at most ~€535k a year on average: a maximum too.

Company selected

Savy ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Pelleautier (05000) · headcount 6 to 9 employees · SIREN 798394391

Number 7 by amount of the 65 contracts Gap published for 2020. It belongs to the policy Culture, sport and youth.

Other contracts of Savy Construction in Gap

Travaux d’extension du Hall de la Blâche2019 · maximum over 5 months137€kConstruction vestiaires stade bayard2019 · maximum over 4 months61€kConstruction de vestiaires pour le stade bayard2019 · maximum over 4 months58€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.