Public contracts of Géovreisset · 2025 · Professional services

Maîtrise d’œuvre pour la restructuration et la rénovation thermique de la maison Peysson

€147k
maximum contract amount over 3.5 years — what was paid on it is not published
Signed on 22 April 2025 · running until about July 2028 · 3.5 yrs
Ongoing22 Jul 2028

That is at most ~€45k a year on average: a maximum too.

Company selected

CVF StructuresIngénierie, études techniques · registered office Lons-Le-Saunier (39000) · headcount 3 to 5 employees · SIREN 410577068

A contract awarded to a consortium of 5 holders; above, the main holder. With it: AUM Pierre Minassian, Économia, Genie Acoustique, Bureau A. Lazzarotto (BET Lazzarotto Fluides). The amount is the whole contract’s: the DECP does not publish each holder’s share.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.