Public contracts of Graveson · 2020 · Construction and buildings

Construction d’un complexe sportif à Graveson : clos couvert

€1.8M
maximum contract amount over 12 months — what was paid on it is not published
Signed on 23 December 2020 · ended around December 2021 · 12 months

Company selected

SMC2Ingénierie, études techniques · registered office Mornant (69440) · headcount 50 to 99 employees · SIREN 450758404

The largest of the 8 contracts Graveson published for 2020. It belongs to the policy Culture, sport and youth.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.