Public contracts of Hirel · 2022 · Construction and buildings

Réhabilitation d’un bâtiment en centre d’accueil de groupes : gros œuvre, démolitions, voirie

€200k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 14 March 2022 · ended around March 2023 · 12 months

Company selected

—Construction d'autres bâtiments · registered office Saint-Herblain (44800) · headcount 250 to 499 employees · SIREN 320116916

The competition

8 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 13 contracts Hirel published for 2022.

Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no