Public contracts of Hirtzbach · 2022
Réhabilitation d’une maison communale en nouvelle mairie lot 01B
Number 3 by amount of the 3 contracts Hirtzbach awarded in 2022.
Contract · Construction and Bâtiment · carried out in 68118
44k €
contract ceiling — what was paid on it is not published
Who won it
Altkirch ConstructionSIREN 802989038The competition
Number of bids not published for that year: the field is only systematic from 2024.
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceFerme et actualisable
Published amendments1
Other contracts of Altkirch Construction in Hirtzbach
Réhabilitation d’une maison communale en nouvelle mairie lot 01A202292k€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.