Travaux extension et rénovation de l école maternelle du ried

The largest contract Hœnheim awarded in 2022, out of 33.

Contract · Construction and Bâtiment · carried out in 67800

3€M
contract ceiling — what was paid on it is not published
Signed on 1 September 2022 · running until about January 2027 · 4.3 yrs
Ongoing1 Jan 2027

Who won it

Société D'Aménagement et D'Équipement du Rhin SuperieurSIREN 578505687

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceFerme et actualisable
Published amendmentsnone

Other contracts of Société D'Aménagement et D'Équipement du Rhin Superieur in Hœnheim

Extension rénovation école maternelle du ried20255.4M€La Ville de Hoenheim souhaite confier à un tiers une délégation pour la représenter en tant que maître d’ouvrage dans le cadre des travaux d’extension et de rénovation de l’Ecole maternelle du…2025198k€Délégation MOA école maternelle ried2025198k€MOA déléguée maternelle du ried202287k€