Skip to main content
Qipu

Public contracts of Houssen · 2022

Extension et réhabilitation Ecole Primaire - Lot 08 Menuiseries Intérieures Bois - Portes

Number 6 by amount of the 16 contracts Houssen awarded in 2022.

Original label (DECP) : « Extension et réhabilitation Ecole Primaire - Lot 08 Menuiseries Intérieures Bois - Portes » · Contract · Construction and Bâtiment · carried out in 68125

228k €
contract ceiling — what was paid on it is not published
Signed on 8 November 2022 · ended around December 2024 · 2.1 yrs
Ended8 Dec 2024

Who won it

GiamberiniSIREN 434386116

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceRévisable
Published amendmentsnone

Other contracts of Giamberini in Houssen

Extension et réhabilitation de l’école élémentaire - Lot 01 Terrassement VRD Paysage2025472k€Extension et réhabilitation Ecole Primaire - Lot 08 Menuiseries Intérieures Bois - Portes2025247k€Extension et réhabilitation de l’école élémentaire - Lot 01 Terrassement VRD Paysage2022456k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method
Extension et réhabilitation Ecole Primaire - Lot 08 Menuiseries…: 228 k€, Houssen 2022 · Qipu