Travaux pour la construction d’un hall des sports

Ascenseur

€44k
maximum contract amount over 21 months — what was paid on it is not published
Signed on 18 March 2024 · ended around December 2025 · 21 months

That is at most ~€25k a year on average: a maximum too.

Company selected

TK Elevator FranceAutres travaux d'installation n.c.a. · registered office Angers (49000) · headcount 1,000 to 1,999 employees · SIREN 722024742

Number 68 by amount of the 74 contracts Illkirch-Graffenstaden published for 2024. It belongs to the policy Culture, sport and youth.

Other contracts of TK Elevator France in Illkirch-Graffenstaden

Travaux pour la construction d’un hall des sports à…2024 · maximum over 22 months44€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.