Public contracts of Ingré · 2020 · Construction and buildings

Travaux de rénovation des sanitaires filles/garçons de l’école élémentaire du moulin a Ingré

€6k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 29 April 2020 · ended around June 2020 · 2 months

Company selected

SARL Peixoto (MP 2000)Travaux de plâtrerie · registered office Sandillon (45640) · headcount 6 to 9 employees · SIREN 502401953

Number 10 by amount of the 11 contracts Ingré published for 2020. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.