Public contracts of Toulouse Métropole · 2022

Travaux de réhabilitation des réseaux EU et EP sur le territoire de TM

€26.1M
framework agreement: a maximum envelope for orders over 5.5 years, not spending — what was paid on it is not published
Signed on 28 July 2022 · running until about January 2028 · 5.5 yrs
Ongoing27 Jan 2028

That is at most ~€4.7M a year on average: a maximum too.

Company selected

Sogea Sud HydrauliqueConstruction de réseaux pour fluides · registered office Perols (34470) · headcount 100 to 199 employees · SIREN 327745394

A contract awarded to 8 holders; above, the main holder. With it: Société Nouvelle Thomas et Danizan Midi Pyrenees, Subterra, Rehacana, Société Eurea, Soc la Garonne, Valentin, Uveo. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 4 by amount of the 413 contracts Toulouse Métropole published for 2022.

Other contracts of Sogea Sud Hydraulique in Toulouse Métropole

Travaux de renforcement des réseaux d’eaux usées et d’eau potable2026 · maximum over 10 months2.5€MTravaux d’assainissement, d’eaux pluviales, d’eau potable…2024 · maximum over 8 years116€MTravaux d’assainissement EU, EP et AEP ; commune de Toulouse…2024 · maximum over 10 months4.3€M
Contract details (procedure, price, amendments, lots)

Procedure : Procédure négociée avec mise en concurrence préalable

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Révisable

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.