Public contracts of Izon · 2024 · Construction and buildings

Construction d’une halle sportive : bâtiment textile

€535k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 21 June 2024 · ended around June 2025 · 12 months

Company selected

SMC2Ingénierie, études techniques · registered office Mornant (69440) · headcount 50 to 99 employees · SIREN 450758404

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 7 contracts Izon published for 2024. It belongs to the policy Culture, sport and youth.

Other contracts of SMC2 in Izon

Création d’un boulodrome couvert2025 · maximum over 10 months208€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 4

Subcontracting declared : yes

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.