Skip to main content

Public contracts of Jacob-Bellecombette · 2022 · Construction and buildings

Création d’un club house tennis

€112k
maximum contract amount over 6 months — what was paid on it is not published
Signed on 30 November 2022 · ended around June 2023 · 6 months

Who won it

Greg ConstructionsTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Arbin (73800) · headcount 20 to 49 employees · SIREN 798456737

Number 7 by amount of the 17 contracts Jacob-Bellecombette published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.