Public contracts of L'Hermitage · 2020 · Construction and buildings

Construction d’un accueil de loisirs

Terrassement voirie et réseaux divers

€77k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 24 December 2020 · ended around April 2022 · 16 months

That is at most ~€57k a year on average: a maximum too.

Company selected

Ruellan Michel et FilsTravaux de terrassement courants et travaux préparatoires · registered office Saint-Vran (22230) · headcount 10 to 19 employees · SIREN 451292700

The competition

80 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 6 by amount of the 16 contracts L'Hermitage published for 2020.

Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.