Skip to main content

Public contracts of La Chapelle-Chaussée · 2024 · Professional services

Maîtrise d’oeuvre salle association et vestiaires football

€48k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 22 March 2024 · ended around March 2026 · 2 yrs

That is at most ~€24k a year on average: a maximum too.

Company selected

Clarc (Couasnon et Launay Architectes)Activités d'architecture · registered office Betton (35830) · headcount 3 to 5 employees · SIREN 497712158

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 3 by amount of the 4 contracts La Chapelle-Chaussée published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.