Construction d’une salle pluricuturelle à La Haye

Carrelage Faience

€50k
maximum contract amount over 20 months — what was paid on it is not published
Signed on 6 July 2022 · ended around March 2024 · 20 months

That is at most ~€30k a year on average: a maximum too.

Company selected

Fautrat B.T.P.Construction d'autres bâtiments · registered office Lessay (50430) · headcount 20 to 49 employees · SIREN 419631460

Number 17 by amount of the 18 contracts La Haye published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.