Lot no2-Démolition

Gros Oeuvre

€60k
maximum contract amount over 9 months — what was paid on it is not published
Signed on 9 December 2022 · ended around September 2023 · 9 months

Company selected

Tison & GailletConstruction de maisons individuelles · registered office Soorts-Hossegor (40150) · headcount 20 to 49 employees · SIREN 428567275

Number 16 by amount of the 29 contracts Labenne published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none