Skip to main content

Public contracts of Lacapelle-Marival · 2025 · Construction and buildings

Rénovation des ateliers municipaux : démolition, gros œuvre, carrelage et faïence

€58k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 13 January 2025 · ended around September 2025 · 8 months

Company selected

Descargues OlivierTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Lacapelle-Marival (46120) · headcount 10 to 19 employees · SIREN 501428015

The largest of the 2 contracts Lacapelle-Marival published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.