Public contracts of Laragne-Montéglin · 2021 · Professional services

Maîtrise d’œuvre pour la construction d’une maison de santé

€207k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 16 December 2021 · ended around December 2023 · 2 yrs

That is at most ~€104k a year on average: a maximum too.

Company selected

Sud Études EngineeringIngénierie, études techniques · registered office Les Mees (04190) · headcount 6 to 9 employees · SIREN 384421871

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Agence Deux Neviere. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The largest of the 4 contracts Laragne-Montéglin published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 3

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.