Public contracts of Lardy · 2019 · Construction and buildings

Aménagement de locaux administratifs

€241k
contract ceiling — what was paid on it is not published
Signed on 12 July 2019 · ended around November 2019 · 4 months

Who won it

Entreprise Destas et CreibConstruction d'autres bâtiments · registered office Itteville (91760) · headcount 20 to 49 employees · SIREN 325698041

Main holder, with the largest amount. The contract has 6 holders; the others are not shown here yet.

The largest of the 5 contracts Lardy published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.