Skip to main content

Public contracts of Le Buisson · 2025 · Construction and buildings

Requalification de logements

Électricité

€57k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 3 February 2025 · ended around May 2026 · 15 months

That is at most ~€45k a year on average: a maximum too.

Company selected

Lozere Électricité Automatisme (Rodier Électricité Automatisme)Travaux d'installation électrique dans tous locaux · registered office Le Buisson (48100) · headcount 3 to 5 employees · SIREN 791412901

Number 6 by amount of the 7 contracts Le Buisson published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.