Public contracts of Le Gosier · 2025 · Construction and buildings

Accord-cadre mixte multi attributaires de travaux multi techniques pour les besoins de la Ville du Gosier

€400k
framework agreement: a maximum envelope for orders over 2 years, not spending — what was paid on it is not published
Signed on 9 October 2025 · running until about October 2027 · 2 yrs
Ongoing10 Oct 2027

That is at most ~€200k a year on average: a maximum too.

Company selected

Entreprise Générale d'Electrification Rationnelle (Axians Antilles)Travaux d'installation électrique dans tous locaux · registered office Baie-Mahault (97122) · headcount 50 to 99 employees · SIREN 311772925

A contract awarded to 2 holders; above, the main holder. With it: Cee Caraibes. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

3 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 11 by amount of the 95 contracts Le Gosier published for 2025.

Other contracts of Entreprise Générale d'Electrification Rationnelle (Axians Antilles) in Le Gosier

Électricité courant fort et faible2025 · maximum over 12 months200€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.