Travaux d’aménagement de locaux pour la direction de la famille à la cuisine centrale de la ville du Gosier (du

Déclaré )

€329k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 12 September 2025 · running until about January 2027 · 16 months
Ongoing12 Jan 2027

That is at most ~€247k a year on average: a maximum too.

Company selected

Société Antillaise de Travaux (Satra)Travaux de maçonnerie générale et gros œuvre de bâtiment · registered office Le Moule (97160) · headcount 6 to 9 employees · SIREN 887850253

The competition

2 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 16 by amount of the 95 contracts Le Gosier published for 2025.

Other contracts of Société Antillaise de Travaux (Satra) in Le Gosier

Travaux de réhabilitation du bâtiment de la police municipale au Bourg…2026 · maximum over 8 months161€kSecond oeuvre2026 · maximum over 12 months143€kGros oeuvres2025 · maximum over 2 years288€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.