Skip to main content

Public contracts of Le Gosier · 2024 · Construction and buildings

Travaux d’aménagement de locaux pour la direction de la famille à la cuisine centrale de la ville du Gosier (du

Déclaré et du · Déclaré )

€174k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 27 November 2024 · ended around March 2026 · 16 months

That is at most ~€130k a year on average: a maximum too.

Company selected

Bâtiments Sécurité ÉlectricitéTravaux d'installation électrique dans tous locaux · registered office Baie-Mahault (97122) · headcount 6 to 9 employees · SIREN 420673733

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 34 by amount of the 70 contracts Le Gosier published for 2024.

Other contracts of Bâtiments Sécurité Électricité in Le Gosier

Fluides2026 · maximum over 12 months229€kÉlectricité courants forts et faibles climatisation plomberie2024 · maximum over 2 years133€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.