Public contracts of Le Haillan · 2020 · Construction and buildings

Extension école élémentaire Luzerne

Revêtements sols et murs

€89k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 9 June 2020 · ended around September 2021 · 15 months

That is at most ~€71k a year on average: a maximum too.

Company selected

Revetements Duret SolsTravaux de revêtement des sols et des murs · registered office Mios (33380) · headcount 6 to 9 employees · SIREN 797427150

Number 9 by amount of the 11 contracts Le Haillan published for 2020. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.