Agrandissement de l’école maternelle Jaurès

€194k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 4 April 2023 · ended around July 2024 · 15 months

That is at most ~€155k a year on average: a maximum too.

Company selected

LTDF - les Techniciens des Fluides (les Techniciens des Fluides)Travaux d'installation d'équipements thermiques et de climatisation · registered office Saint-Maur-Des-Fosses (94100) · headcount 20 to 49 employees · SIREN 722040078

Number 8 by amount of the 18 contracts Le Mesnil-le-Roi published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.