Public contracts of Le Poiré-sur-Vie · 2025 · Construction and buildings

Électricité

Panneaux photovoltaïques · Construction d’une salle de danse, gymnastique et fitness…

€56k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 9 October 2025 · running until about January 2027 · 15 months
Ongoing9 Jan 2027

That is at most ~€45k a year on average: a maximum too.

Company selected

Snge OuestTravaux d'installation électrique dans tous locaux · registered office La Roche-Sur-Yon (85000) · headcount 10 to 19 employees · SIREN 518879861

Number 32 by amount of the 63 contracts Le Poiré-sur-Vie published for 2025.

Other contracts of Snge Ouest in Le Poiré-sur-Vie

Construction salle danse, gym site Idonnière lot 12-Électricité…2025 · maximum over 15 months56€kÉlectricité courants forts et faibles2024 · maximum over 2 years142€kPhotovoltaïque2024 · maximum over 2 years129€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.