Skip to main content

Public contracts of Le Teich · 2025 · Construction and buildings

Réparation des pieux de la Maison de la Nature du Bassin d’Arcachon

€200k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 9 December 2025 · ended around April 2026 · 4 months

Company selected

BalineauConstruction d'ouvrages maritimes et fluviaux · registered office Pessac (33600) · headcount 50 to 99 employees · SIREN 394877021

The competition

1 bid received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 48 contracts Le Teich published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.