Public contracts of Lesquin · 2020
CONSTRUCTION D’UNE ECOLE ELEMENTAIRE - Rue Henri Ghesquière: Lot 8: CARRELAGE - FAIENCE
Number 28 by amount of the 48 contracts Lesquin awarded in 2020.
Original label (DECP) : « CONSTRUCTION D’UNE ECOLE ELEMENTAIRE - Rue Henri Ghesquière: Lot 8: CARRELAGE - FAIENCE » · Contract · Construction and Bâtiment · carried out in 59810
97k €
contract ceiling — what was paid on it is not published
Who won it
Batisol et ResineSIREN 840016299The competition
Number of bids not published for that year: the field is only systematic from 2024.
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceFerme et actualisable
Published amendmentsnone
Other contracts of Batisol et Resine in Lesquin
Construction du groupe scolaire la motte: lot 9: sols souples (CGD) / résine de sol2021191k€CONSTRUCTION D’UNE ECOLE ELEMENTAIRE - Rue Henri Ghesquière: Lot 9: REVETEMENTS DE SOLS202076k€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.